Construction of two mooring dolphins and two berthing dolphins as well as a 250T concrete platform on piles and a 90ml footbridge. NEGRI also installed loading arms on the structure and proceeded with the construction of four pipelines (3 of 8 inches and 1 of 10 inches), one aerial section, and one 140ml section in a dredged spoil by the company, connecting the working platform and a valve chamber. As part of its work, NEGRI demolished an old structure at a depth of 10ml with a 100T BRH excavator.

Date
2020
localisation
Douala, Cameroon